Access Scaffold to Internal Light Wells at India Buildings

As part of the this major scaffolding package we have just completed the access scaffold to the two internal light wells in the building which are each 34 metres long by 14 metres wide and over 30 metres high.

The scaffold system we used is the Metrix System mainly because it was around half the weight of conventional scaffolding. 

This was a major factor in deciding to use the system as everything had to be taken into the building by hoist and then by pallet truck across the floors and taken into the lightwells.

Another reason for using the system was we had to fasten the scaffold to the walls of the light wells as the roof below could not take the weight of the scaffold.

In all we saved 80 tons in weight in the two light wells alone and we therefore completed the work in half the time.