We assembled the public access staircases during the day, prior to assembling the footbridge, in the car park compound on site.
We then craned the footbridge onto the support towers during one night time posession of the track meaning the whole structure only took one night to install.
The whole assembly is fully compliant with public access and Network Rail regulations.
Watch our installation video through our LinkedIn profile!
"We, AMCO Giffen, know we will get a reliable and professional service from Crossway that is why they are an approved and trusted supplier for us. The footbridge had to be landed within a specific possession and Crossway comfortably achieved this date. When removing the existing bridge at Garforth the team worked exceptionally well under time pressure and went above their requirement by assisting AMCO Giffen installing lateral constraints between the bridge and the scaffold structure."